TITLE:
CONSTRUCTION/UPGRADE OF AWALI HOSPITAL SOUTH EAST (SE) WING.
Title in Arabic:
بناء/ترقية الجناح الجنوبي الشرقي لمستشفى عوالي.
Brief scope of work in English:
Existing South East wing to be demolished and new patient rooms, delivery rooms and wards to be newly constructed.. The existing buildings within the construction area will be safely demolished to make way for the new facility. This upgraded facility will support the Royal Intensive Care Unit and the planned Awali Hospital expansion project.
Scope of Work in Arabic
سيتم هدم الجناح الجنوبي الشرقي الحالي وإنشاء غرف جديدة للمرضى وغرف الولادة والأجنحة. وسيتم هدم المباني الحالية داخل منطقة البناء بأمان لإفساح المجال للمنشأة الجديدة.
ستدعم هذه المنشأة التي تمت تطويرها وحدة العناية المركزة الملكية ومشروع التوسعة المخطط له في مستشفى العوالي.
,
2.1 | MANDATORY CRITERIA |
A | WORKS EXPERIENCE: |
BIDDERs must have a minimum of 5 years of experience insuccessful execution of civil engineering and/or building project works(material procurement, manpower and equipment hire contracts/agreements areexcluded) and BIDDERs must havecompleted at least one project ofminimum value BHD 500,000.00 in Bahrain or any other Gulf/Middle Eastcountries in the last 5 years.
BIDDERs should provide with their bid response, for review by the Companyas part of the bid evaluation process, a proof of their previous experiencerelevant to the provision of the services that are required as specifiedherein, in the form of copies of Client letters of reference/ credentialsfrom Clients/ completion certificates issued by Clients, including contractstart and completion dates, contract and PO values, etc. The relevantsupporting documents submitted shall also include the current and validcontact information (address, contact numbers, contact emails etc.) forverification by Bapco. Non-submission of any of the information will resultin the disqualification of the bid. |
B | HEALTH, SAFETY & ENVIRONMENT: |
BIDDERs should have and demonstrate thefollowing: |
1) Fully auditable and active HSEPolicy, HSE Procedures relevant to onsite activities and Safety Training Planin operation within their organization |
2) Accreditation with acertificate for OHSAS 18001 or ISO 45001, which are currently valid or in theprocess of re-validation. Documentary evidence should be submitted tosubstantiate the above and its validity, or other proof if the bidder is inthe process of revalidation. |
C | QUALITY AND ENVIRONMENT CERTIFICATIONS: |
TheContractor shall be accredited with formal certification for ISO 9001 and ISO14001, which is currently valid or in the process of re-validation.Documentary evidence shall be submitted to substantiate the above and itsvalidity, or other proof if the bidder is in the process of revalidation. |
|